Reject hours - Approve task updates - PS 2007 RRS feed

  • Question

  • Hi ,

     We are using project server 2007.

    Project manager in PWA approves tasks in Approve task updates. Now if a team member submits time for 3 weeks, and if PM feels the hours filled for one week out of 3 weeks is wrong, can we work out on an option to ensure PM only rejects those hours of a week.

    Can the PM have option to reject only the hours he/she wants to.

    In current scenario PM if he/she rejects it rejects the whole timesheet submited by team member.

    Thanks

    mp

    Monday, April 23, 2012 10:10 AM

Answers

  • MP --
     
    The answer to your question is no, you cannot approve part of a task update and reject the rest.  Approval and rejection of task updates are an all or nothing proposition.  You either approve the entire task update, or you reject the entire task update.  In your example, I would recommend the PM reject the update and tell the team member how to correct the update.  Then the team member should submit it to you again for approval.  Hope this helps.

    Dale A. Howard [MVP]
    VP of Educational Services
    msProjectExperts
    http://www.msprojectexperts.com
    http://www.projectserverexperts.com
    "We write the books on Project Server"

    • Marked as answer by Mac_cs Tuesday, April 24, 2012 4:46 AM
    Monday, April 23, 2012 10:09 PM
    Moderator

All replies