none
Question / Project 2007 / To-do List? RRS feed

  • Question

  • OK, so, this is a totally n00bish question, but:

    What would you suggest is the easiest way to show a list of "who is working on what this week" in Project 2007?

    It's kind of similar to the "To-Do List," but what I really want is, just for this week, what is everyone working on?

    Thoughts?

    ~Steve

    Thursday, December 1, 2011 4:26 PM

Answers

  • Steve,

    Right next to the "To-do list" report is the "Who does what when" report. Have you looked at that? If that doesn't quite get what you want, apply the "Using resource in date range" filter on the "To-do list" report. If neither of those does what you want, try the "Date Range" filter on the Resource Usage view.

    Hope this helps.

    John

    • Marked as answer by sbattisti Thursday, December 1, 2011 6:08 PM
    Thursday, December 1, 2011 4:37 PM

All replies

  • Steve,

    Right next to the "To-do list" report is the "Who does what when" report. Have you looked at that? If that doesn't quite get what you want, apply the "Using resource in date range" filter on the "To-do list" report. If neither of those does what you want, try the "Date Range" filter on the Resource Usage view.

    Hope this helps.

    John

    • Marked as answer by sbattisti Thursday, December 1, 2011 6:08 PM
    Thursday, December 1, 2011 4:37 PM
  • OK, I think the "Who does what when" report did the trick, at least close enough for now. Thank you! :)

     

    Thursday, December 1, 2011 6:08 PM
  • Steve,

    You're welcome and thanks for the feedback.

    John

    Thursday, December 1, 2011 9:27 PM