Recurring tasks every second year or so... RRS feed

  • Question

  • Hi!

    I try to create a recurring task that will be scheduled every second year or even every fourth year as a part of a maintenance plan.
    What I can figure out from the "Recurring task information" window is that once every year is the limit.
    Does anyone have a workaround on this issue?

    //Sofia

    Thursday, February 12, 2015 8:19 AM

All replies

  • Hi Sofia,

    I cannot test it right now so I might be wrong, but have you tried selecting "yearly" for the recurring pattern and selecting "2" as the recurring number? Doing this the recurring task should be repeated every 2 years. A 4 years recurring task would work the same.


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller |

    Thursday, February 12, 2015 8:26 AM