Actuals work Adjustment RRS feed

  • Question

  • We are using Single Entry mode with actuals protected. Actuals enter through timesheet only. user posted the time (10hrs) in task A which is not suppose to do enter in it. By entering the time in task A, Task A actual start date has been stamped and % complete is marked as 20%. How to recall timesheet for adjustment so that user can update the actual in appropriate task i.e Tas B and marked the task A as 0% complete, so that Actuals work of Task A has to be 0 and Task B should be 10 hrs.

    Thanks

    Farhan


    farhan



    • Edited by Farhan_123 Saturday, April 13, 2013 8:17 PM
    Saturday, April 13, 2013 7:26 PM

Answers

  • Hi Farhan,

    User can open the timesheet and recall the timesheet. After this he can make necessary changes and submit ti for approval.

    Once PM approves the timesheet, all the values will be adjusted accrodingly.


    Vikram Daruru - MSFT

    Thursday, November 7, 2013 11:30 AM
    Moderator

All replies

  • Hi Farhan,

    User can open the timesheet and recall the timesheet. After this he can make necessary changes and submit ti for approval.

    Once PM approves the timesheet, all the values will be adjusted accrodingly.


    Vikram Daruru - MSFT

    Thursday, November 7, 2013 11:30 AM
    Moderator
  • Farhan,

    User cannot recall a timesheet from a timesheet. To recall, the user has to 

    1) Navigate to "Manage Timesheets" page from the quick launch.

    2) Highlight the row of the timesheet that needs to be recalled

    3) Click the Recall Button on the ribbon.

    4) once the timesheet is recalled, and the status shows "In Progress, the user can navigate to the timesheet itself, and make any adjustments and resubmit the timesheet.


    Prasanna Adavi,PMP,MCTS,MCITP,MCT http://thinkepm.blogspot.com

    Thursday, November 7, 2013 12:46 PM