Cost resources usgae in PWA 2013 RRS feed

  • Question

  • Hi,

    PWA 2013 :

    Can we conceive a view where a user can easily enter scheduled Costs and then Actual Costs, using Cost Resources for expenses like travel, hostel, restaurant… on a time scale such as the timesheet for Work resources.

    Thanks

    Tuesday, November 5, 2013 10:21 PM

Answers

  • Hi,

    I'm afraid that this is not possible in PWA (even 2013 version). None of the project views display a timephased view, but only Gantt chart.

    In order to do that, you have to use Project Pro with the usage views (either resource or task).

    Hope this helps.


    Guillaume Rouyre - MBA, MCP, MCTS

    • Marked as answer by Robert6156 Sunday, November 10, 2013 5:57 PM
    Sunday, November 10, 2013 4:06 PM