none
Project Server 2013 Project Schedule RRS feed

  • Question

  • Hi All,

    When the project is created from project center is it possible to automatically add the project name as high level task and the start date to the project schedule.



    Thanks in advance, Taj

    Monday, March 9, 2015 9:44 AM

Answers

  • Hi,

    just a short addition to the answer of Guillaume: To display the project summary task, create the project, navigate to the schedule and click on the ribbon "options" and check "Project Summary Task.

     


    BR,

    Julian

    Senior Consultant

    Blog: https://project-brain.com

    Note: Posts are provided “AS IS” without warranty of any kind, either expressed or implied, including but not limited to the implied warranties of merchantability and/or fitness for a particular purpose.



    Saturday, May 20, 2017 7:21 AM

All replies

  • Hi Taj,

    For the project name, the project summary row (task 0) by default takes the project name. I'd suggest you to display this project summary row in your project Templates so it will be visible with the project name for all projects.

    For the start date, you already have the start date in the project creation page by default.


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller |

    Monday, March 9, 2015 10:02 AM
    Moderator
  • Hi,

    just a short addition to the answer of Guillaume: To display the project summary task, create the project, navigate to the schedule and click on the ribbon "options" and check "Project Summary Task.

     


    BR,

    Julian

    Senior Consultant

    Blog: https://project-brain.com

    Note: Posts are provided “AS IS” without warranty of any kind, either expressed or implied, including but not limited to the implied warranties of merchantability and/or fitness for a particular purpose.



    Saturday, May 20, 2017 7:21 AM