Project Server 2010 Queue Clean up job not triggering automatically RRS feed

  • Question

  • All,

    In our production environment (PS 2010 SP2 + March 2015 CU) we have set up Queue Clean up settings as below:

    Cleanup Interval: 720 (i.e. 30 days)

    Cleanup Interval Offset: 0 (12 am)

    Cleanup Age Limit For Successful Jobs: 1440

    Cleanup Age Limit For Non-Successful Jobs: 1440

    but, when I ran a query on Project Queue Cleanup job query results show clean up did run get triggered periodically (as shown below), due to which there is large queue archive data in the tables. We want to clean up this old queue data.

    Can any one suggest how do we manually trigger queue clean up job in Project Server 2010 and also how to make sure that this jobs run properly and clears the old queue data as per the settings defined?

    Monday, June 18, 2018 8:16 PM