Days start at 6am RRS feed

  • Question

  • I want to change the main times for my day to have it start at 6am and end at 6am. I can change everything that I can think of, but reports still start the day at midnight. Our shift schedules are 6am-6pm and 6pm-6am. It would really help if Project wouldn't start it's day until 6am.
    Tuesday, January 8, 2013 3:05 PM

All replies

  • Okay - what have you done to change the times?  Changed the working calendar through Project tab, Change Working time?  Set the options appropriately in File > Options?

    What version of project please?

    Tuesday, January 8, 2013 3:10 PM
    Moderator
  • Adding to Julie's comments, which report are you referring to?

    Sapna Shukla

    Tuesday, January 8, 2013 4:00 PM
    Moderator
  • Ah, I've just re-read your post in a bit more detail.  No matter what the working time definition is (6:00 am to 6:00 pm or 6:00 pm to 6:00 am) a day does start at midnight.

    So, for the 6:00 pm to 6:00 am schedule you'd need to see:

    6:00 pm to 12:00 am and the next day 12:00 am to 6:00 am.

    Is this what you are referring to?

    Tuesday, January 8, 2013 4:18 PM