Can we have multiple team resource assign to a task in Project Server 2010 ? RRS feed

  • Question

  • Hi all,

    We are trying to find a solution for a situation as described below:

    We want to assign a "Task 1" for "5 days duration" to "2 Resources" with a "40 hours fixed work"(not for 80 hours), where each resource would have "100% units" (Ideally), in order to fill the full timesheet for 5 days alone (if needed). Also, the each day work hours are "8 hrs".

    In simple words, any of the 2 resources should be allowed to report all 40 hours. 

    Since, in above scenario when we set "Fixed Work", it retains the 40 hours work and 5 days duration and divide the total work hours by 2 (20 for each resource) so the number of planned hours decrease to 4 hrs for each day (5 days). Moreover, if the resource reports full 8 hrs each day he/she works, it increase the task's Work Hours to extra 20 and which become 60 hrs. But, we want that the other resource's hours should not considered since the task has been completed by the first resource already (other resource's reporting should go extra over 40 hours if reported).

    Hope, I am able to explain the issue. Please advice....

    Thanks in advance for any suggest.

                                                                                                                                                               

    Monday, May 30, 2016 1:00 PM