none
Project Server 2013 - Approved Tasks not applied to Project Schedule RRS feed

  • Question

  • Environment Details: Microsoft Project Server 2013 SP1

    When an Resource completes a tasks within the Task or Timesheet page at the end of each day, the tasks is routed to the Project Owner for approval. The Project Owner (Project Manager) approves the task. During this process no errors are displayed.

    When the Project Owner (Project Manager) goes into the Project Professional 2013 client to view how the project is progressing, and update the project completion date, the updates is not applied to the project. 

    This worked for some time, but has recently stopped working with no changes made to the environment. Any help would be great, as our project manager's are manually updating the tasks prior to approving them so they can report back on the project each week. 

    Wednesday, May 21, 2014 9:52 PM

All replies

  • Hello ProjMgrMatt

    Sounds pretty serious, but I think something is missing somewhere.

    Make sure that the Status Manager field is the same as the Project Owner. 

    Check to queue to be sure that nothing is stuck and waiting.

    Create a new project, publish, submit, approve, etc and see if it still happens.

    Cheers!.


    Michael Wharton, MVP, MBA, PMP, MCT, MCTS, MCSD, MCSE+I, MCDBA
    Website http://www.WhartonComputer.com
    Blog http://MyProjectExpert.com contains my field notes and SQL queries

    Thursday, May 22, 2014 2:37 AM
    Moderator