    when i open a project in Project professionl the Tasks level  total sum of actuals are not matching with the resources actulas.

    for example Task A has actulas as 3000 but when i expanded the task and when summed the resources actuals (5000) the total is not matching  i.e., the rolllup of actuals at task level is not matching with the total of individual resource actuals.

    can anyone help us to match up the actuals amount?

     

     

    Wednesday, June 8, 2011 6:23 PM

Answers

  • Make sure that resources are not assigned to summary tasks.  You can get different strange results like this if you do.

    Cheers!


    Michael Wharton, MBA, PMP, MCT, MCSD, MCSE+I, MCDBA
    www.WhartonComputer.com
    Wednesday, June 8, 2011 7:22 PM