Project Information Form and workflow-controlled fields RRS feed

  • Question

  • In MS Project 2010 the project information form displayed the "Sample...." field (workflow-controlled) data, but did not allow it to be edited in MSP

    In MSP Project 2013 the data associated with workflow-controlled fields is not displayed.

    Is this change by design or a bug?

    rgds

    Mike


    Mike Mahoney

    Monday, March 4, 2013 12:21 PM

All replies

  • A follow up on this: In 2013 the "absence" of data in a workflow-controlled field in MSP means the field cannot be used in task level calculation. This is possible in 2010.

    A scenario for this is; update then lockdown a tolerance value in a PDP. The calculated task field makes use of this value to determine if a variance is within tolerance.

    rgds


    Mike Mahoney