  • I can run a manual tape backup by right clicking on the volume and choosing Long term backup, but it only runs the monthly tape backup job.

    How can I manually run a Yearly Tape backup job?

    I am using DPM 2010.

    There must be a way to create a job that uses Yearly backup settings.  

    Or an alternative is to change the expiry date of the Backup if that is possible.

    Thanks,

    Thursday, April 30, 2015 7:27 PM

All replies

  • Although you cannot pick the recovery point date in the past to make a new recovery point from, you can run the DPM Power shell script in this post to select a recovery goal to make a current backup for.  The recovery point date would be that of the latest disk based recovery point for any goal selected.


    Please remember to click “Mark as Answer” on the post that helps you, and to click “Unmark as Answer” if a marked post does not actually answer your question. This can be beneficial to other community members reading the thread. Regards, Mike J. [MSFT] This posting is provided "AS IS" with no warranties, and confers no rights.

    Friday, May 1, 2015 2:31 AM
    Moderator