Portfolio Analysis - New Start Date RRS feed

  • Question

  • Hello All,

    I'm doing a portfolio analysis for some proposed projects, and when doing my what-if's, I want to change the Start Date. Some of the projects allow me to provide a new start date, and others are greyed out, and these projects schedules are very much alike for demo purposes. Any clues for the clueless are always greatly appreciated! 

    Cheers, Ray

    Tuesday, September 4, 2018 6:58 PM

Answers

  • Ray --

    Is it possible the Finish date of the grayed out projects extends beyond the End date of the Analysis?  When I know there is a possibility of needing to delay some projects, I add a year onto the time span for the analysis so that I can delay projects if needed.  Just a thought.  Hope this helps.


    Dale A. Howard [MVP]

    Tuesday, September 4, 2018 7:49 PM
    Moderator
  • You are more than welcome for the help, my friend!  :)


    Dale A. Howard [MVP]

    Tuesday, September 4, 2018 8:05 PM
    Moderator

All replies

  • Ray --

    Is it possible the Finish date of the grayed out projects extends beyond the End date of the Analysis?  When I know there is a possibility of needing to delay some projects, I add a year onto the time span for the analysis so that I can delay projects if needed.  Just a thought.  Hope this helps.


    Dale A. Howard [MVP]

    Tuesday, September 4, 2018 7:49 PM
    Moderator
  • Thanks Dale, that was it!

    Tuesday, September 4, 2018 8:03 PM
  • You are more than welcome for the help, my friend!  :)


    Dale A. Howard [MVP]

    Tuesday, September 4, 2018 8:05 PM