Not importing Start and Duration from Excel RRS feed

  • Question

  • Hi,

    I am importing task data from Excel to MSProject. I have mapped the data and it all imports into MSProject OK using the Append option, except Start is not imported and all Duration fields are set to 0 days.

    To import these two correctly, I have to do a follow-up import using the Merge option. This works, but obviously it would be best if they were included correctly in the first Append import. 

    Duration is in days and format General. Start is in format d/mm/yyyy hh:mm.

    Excel and Project versions are both MS Office 365.

    Any suggestions as to why they are not included in the Append import?

    Tuesday, July 16, 2019 1:02 PM