Table Source For Earned Value Data RRS feed

  • Question

  • Hi,

        the organization I work for has moved from on prem PWA to Project Online for improved collaboration with partners etc. One thing we are interested in is the ability to generate real time earned value over time reports of projects within a program of work. 

    I have been able to connect to the OData data source however I am not familiar with the data model and wanted some guidance on which tables are the source of earned value data to generate the earned value over time report for multiple projects.

    Thanks

    Tony

    Friday, November 25, 2016 3:01 PM

All replies

  • Hi Tony Hamill, 

    You can check the Assignments table ( when you have resources assigned to tasks)

    Also Table Tasks or Tasks Timephased Data Set.

    Depends which information you want to see. 

    Use the defaul URL and open all tables 

    https://domain/sites/PWA Name/_api/ProjectData


    Diego Campos Pereira PPM Consultant https://diegocampereira.com