none
Cannot assign certain resource in a pool to task RRS feed

  • Question

  • Hi, all,

    I am making a project schedule, which is linked to a resource pool. It is weird enough when I assigned a Cost type resource, "Architectural and Engineering", to a task, it shows there. When I saved, closed, and reopened the file, this loaded resource became a work type resource in the pool, a Project manager "JW", with 0% unit, and a cost figure. The amount of total cost, work were changed too. I tried to delete the task, redo resource loading, but same thing happened. All other resources assigned to this project seems were all right. All other project schedules with same pool, using the "Architectural and Engineering" or "JW" resource,  but no such an issue. To solve this, I even rebuild this specific project schedule, it happened again.

    Could you please tell me what might be the possible reason? Thank you very much!

    Elaine

    Thursday, March 7, 2019 5:54 PM