  • Hi, 

    I am having a problem with my resource assignment. When assigning a resource to a summery task, the summary task is visible in the resource usage in MS Project, however when i enter the Resource center in Project Online, and go to Resource Assignments, the summary task cannot be seen. Why? And what can i do to see it/include it in the resource assignments in Project Online. 

    Thanks!

    Regards, 

    Karen


    Tuesday, November 1, 2016 4:28 PM

Answers

  • Karen,

    Did you check the box that says "Summary Tasks" ? Also, the summary task will appear as an assignment in the list. See the pictire below.

    Having said that, assigning resources to summary task in general is not a good practice. You might want to reconsider this approach.


    Cheers,

    Prasanna Adavi, Project MVP

    Blog:   Podcast:    Twitter:    LinkedIn:   

    Tuesday, November 1, 2016 5:58 PM
    Moderator

All replies

  • Karen,

    Did you check the box that says "Summary Tasks" ? Also, the summary task will appear as an assignment in the list. See the pictire below.

    Having said that, assigning resources to summary task in general is not a good practice. You might want to reconsider this approach.


    Cheers,

    Prasanna Adavi, Project MVP

    Blog:   Podcast:    Twitter:    LinkedIn:   

    Tuesday, November 1, 2016 5:58 PM
    Moderator
  • Thank you very much, Prasanna, I just found the box - so now it works. Sorry for the inconvenience.