Duration format is not changing for all sub tasks upon changing the duration type in project settings RRS feed

  • Question

  • Hi All,

    I've created all the tasks originally with the days duration type. But when I change the duration type to weeks, only the summary tasks are showing in weeks format where as the sub tasks are not changing. Do I need to make any other changes to reflect this or is this the default behavior of MPP?  

    Below is a screenshot for your reference.

    Thanks.


    Rajkumar Allepu (MCP) , | https://sharepointprojectserver.com ** Please mark it as answer if my answer would resolved your issue.

    Monday, March 23, 2020 7:32 AM

Answers

  • Answer: MSP will not change what you have already entered in days and weeks. The summary is not entered data. The change only applies to new tasks or new input. If you type in 10 now you will get 10 weeks.
    Monday, March 23, 2020 8:34 AM

All replies

  • Answer: MSP will not change what you have already entered in days and weeks. The summary is not entered data. The change only applies to new tasks or new input. If you type in 10 now you will get 10 weeks.
    Monday, March 23, 2020 8:34 AM
  • Thank you Trevor for confirming this.

    Rajkumar Allepu (MCP) , | https://sharepointprojectserver.com ** Please mark it as answer if my answer would resolved your issue.

    Monday, March 23, 2020 8:52 AM