none
Clearing Job in Queue recommended before Project Server Migration? RRS feed

  • Question

  • Hi,

    I have done test migration for Project Server 2007 to 2010. Some Time-sheet Jobs were pending in queue before I took the Database backups. Now after migration I am seeing those jobs in queue and not able to restart them either. Is it so that there is some Microsoft recommendation for clearing queue Jobs before migration commences.

    Thanks,

    Bhawna

    Monday, August 19, 2013 5:17 AM

All replies

  • Bhawna,

    There is no such official document to talk about clearing queue jobs, however it's a general and best practice to make sure that all your pending jobs are processed and checked out enterprise entities are checked in.


    Hrishi Deshpande – Senior Consultant DeltaBahn
    Blog | < | LinkedIn

    Please click Mark As Answer; if a post solves your problem or Vote As Helpful if a post has been useful to you.This can be beneficial to other community members reading the thread.

    Tuesday, August 20, 2013 1:10 AM
    Moderator