none
Project graph RRS feed

  • Question

  • I've currently using Resource graph showing work allocation within my resource pool. Since there are several projects that share the same resource pool, is there a way to show a graph by project (Project workload graph)?
    Thursday, March 8, 2012 4:02 PM

Answers

  • Mimi,

    The only way of doing this without a VBA routine is to export the information to Excel and graph it there.  Create a project filter and apply it on the Mapping dialog box during creation of the export map.  Since you have a resource pool, the export must be performed from there, unless you want to do it on each project.


    Gregg D. Richie, PMP, MCTS; Author, Microsoft Project 2010, Microsoft Official Academic Course Series

    Thursday, March 8, 2012 4:50 PM