Project 2010: Do you experience inserted tasks retaining predecessors from task "pushed down"? RRS feed

  • Question

  • I am inserting a series of tasks by using the "insert task" feature.  As a new row is added, it is retaining the predecessor, which should be "pushed down" with the row below.  Have you experienced and resolved this issue?

    Thank you!

    Saturday, October 8, 2011 5:13 PM

Answers

  • Hi PMDenver,

    Welcome to this Microsoft Project forum:)

    Check File/Options/Schedule tab and look for Autolink inserted or moved tasks.  Make sure it's unchecked.

    What version of Project are you using?  Project Server?  SR1 installed?

    FAQs, companion products and other useful Project information can be  seen at this web address:  http://project.mvps.org/faqs.htm

    Hope this helps - please let us know how you get on :)

    Mike Glen
    MS Project MVP
    See http://tinyurl.com/2xbhc for my free Project Tutorials

    Saturday, October 8, 2011 5:56 PM
    Moderator