Roll up @ project level,summary level,assignment level RRS feed

  • Question

  • What is these terms in project online "Roll up at project level, summary level, assignment level"???

    Please brief with example.

    Thanks in advance

     
    Friday, June 21, 2013 6:32 AM

Answers

  • Hi Abbas, I presume you are seeing this term when creating Custom Fields?  Generally it will be asking how you want the field 'rolled-up' or aggregated, at the various levels.  As an example you might have a field representing a numeric quantity that you want added up for each task below a summary, then the total shown for the summary, and the grand total at the project level.  You may have a number representing the risk relating to the task - in which case having the maximum show at the summary and project level may be more appropriate - or another example might be a calculation - where you just want the same formula used at the summary level rather than rolling up any of the numbers.  For assignments there can be more than one assignment per task - so in this case you can choose to roll-down the task level field unless the field is manually entered at the assignment level.

    Does this help you understand the terms?

    Best regards,

    Brian.


    Blog | Facebook | Twitter | Posting is provided "AS IS" with no warranties, and confers no rights.
    Project Server TechCenter | Project Developer Center | Project Server Help | Project Product Page

    Monday, June 24, 2013 6:01 PM
    Owner

All replies

  • Hi Abbas, I presume you are seeing this term when creating Custom Fields?  Generally it will be asking how you want the field 'rolled-up' or aggregated, at the various levels.  As an example you might have a field representing a numeric quantity that you want added up for each task below a summary, then the total shown for the summary, and the grand total at the project level.  You may have a number representing the risk relating to the task - in which case having the maximum show at the summary and project level may be more appropriate - or another example might be a calculation - where you just want the same formula used at the summary level rather than rolling up any of the numbers.  For assignments there can be more than one assignment per task - so in this case you can choose to roll-down the task level field unless the field is manually entered at the assignment level.

    Does this help you understand the terms?

    Best regards,

    Brian.


    Blog | Facebook | Twitter | Posting is provided "AS IS" with no warranties, and confers no rights.
    Project Server TechCenter | Project Developer Center | Project Server Help | Project Product Page

    Monday, June 24, 2013 6:01 PM
    Owner
  • Hi Brian

    What a great explanation you delivered on Roll up, it was really helpful to us.

    Thanks for reply. 


    Thanks and Regards, Sumit Pandey | Consultant

    Wednesday, June 26, 2013 6:10 AM