    there is a way how i can see the montly costs on MS Project?? I need a montly costs for each activity.

    thank you

    Wednesday, December 17, 2014 10:58 PM

All replies

  • Use the Task Usage View. On the grid at the right of the screen, where the Details column has Work, right click and choose Cost from the menu. The right click on the timescale running along the top of the grid and adjust to months.

    You can also use the visual reports to generate the cash flow report.

    Thursday, December 18, 2014 12:07 AM
  • Hi Stugax,

    Yes.

    1.  Change to the the Task Usage view

    2. On the view tab, select Months for the Timescale.

    3. On the Format Tab, deselect work and select Costs from the Details group.

    Your project should look similar to the image below...


    Ben Howard [MVP] | web | blog | book | P2O

    Thursday, December 18, 2014 12:08 AM