  • Question

  • If I set a baseline in my project (for example Baseline 5) and then subsequently alter certain work on that baseline, which table in the reporting database is this stored in? MSP_EMPASSIGNMENT_USERVIEW only hold the original baseline.

    Thanks in advance

    Wednesday, December 7, 2016 12:24 AM

All replies

  • Hi,

    Not sure to understand... If you manually alter a baseline, there is no way to recover it as soon as you published the project plan. 

    What do you mean by "original baseline"? The MSP_EMPASSIGNMENT_USERVIEW table does hold all baseline data from baseline 0 to baseline 10.


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller

    Wednesday, December 7, 2016 8:13 AM