  • Hi PPM Dave,

    In my schedules I tend to use AutoScheduled tasks 99% of the time.  I may use manually scheduled tasks in the following scenario.

    1. During the planning phase, when I'm uncertain of all of the data

    2. During the execution phase, when I have a task that is not dependent on another one - though of course I could easily put a Start No Earlier Than constraint on an AutoScheduled task to do the same thing, but I quite like the fact that the Gantt Bar is visually different.

    You've got a lot of questions coming in, you might be wise to invest in a book or online course...?   It would be a good investment short, mid and long term...


    Ben Howard [MVP] | web | blog | book | P2O

    • Proposed as answer by John - Project Monday, November 30, 2015 4:02 PM
    • Marked as answer by PPM Dave Tuesday, December 1, 2015 9:13 AM
    Monday, November 30, 2015 9:09 AM
    Moderator