    Am working in program that including 24 project

    We called the projects hear (WS) so we have 24 WS

    That mean we have 24 WS leader and more than 50 team members

    I trans all program plan to PWA (More than 2000 task) we grouping the tasks based on the WS like this :

    WS1: Chang management  (Group 1)

    Chang network (group 2)

    Task 1

    Task 2

    Task 3

    -

    -

    -

    Task 50

    WS2: Organization design (Group1)

    Prepare level 1,2,3,4 (Group 2)

    Task 1

    Task 2

    Task 3

    -

    -

    -

    Task 20

    Detailed chats (group 3)

    Task 1

    Task 2

    Task 3

    -

    -

    -

    Task 34

    So I divided all the teams beads on WSs

    Now to managing the resources I have to link Every team to one of the WS

    Win the leader or the member login PWA he well found only his WS

    Authority only for his WS

    Reporting only for his WS

    Timesheet only for his WS

    Reminders only for his WS

    So now is there any way to link Group of tasks to team leader & member ?

    Essay to assign task to rescues but what about the group of task?

    I can’t find a way to link group of task to teams leaders &members

    Can anyone help me in this topic?

    Thanks

    Wednesday, January 30, 2013 8:05 PM

All replies

  • Try using a team resource.  Or created a custom field and specify the groups in the custom field.

    Sort, group or filter by group.


    Michael Wharton, MVP, MBA, PMP, MCT, MCTS, MCSD, MCSE+I, MCDBA
    Website http://www.WhartonComputer.com
    Blog http://MyProjectExpert.com contains my field notes and SQL queries

    • Proposed as answer by Expiscornovus Friday, February 1, 2013 10:58 AM
    Thursday, January 31, 2013 3:57 AM
    Moderator