Resource unites and peak RRS feed

  • Question

  • Hi

    I have the following task as following

     
    Task Mode Task Name Duration Work Peak Resource Names
    Auto Scheduled Initiate 60 days 2 days ExternalBA,IntBA

    the work is distributed 0.05 for external and 1.95 for internal , and its showing me and over allocation on the external resource , there is no conflict in the schedule and if i changed the work load balance to 1 days each the over allocation is resolved , any ideas


    Malek AlShayeb

    Friday, July 12, 2013 1:23 PM

All replies

  • anover view

    Resource Name Work Cost Peak Assignment Units
    ExternalBA 6.5 days 0 9%
       Task 1 1.4 days 0 4% 100%
       Task 2 3.5 days 0 9% 100%
       Task 3 0.4 days 0 1% 100%
       Task 4 1 day 0 1% 100%
       Task 5 0.2 days 0 1% 100%

    Malek AlShayeb

    Friday, July 12, 2013 1:43 PM