none
Fixed Start with FF constraint RRS feed

  • Question

  • I have a task 2 that has a start date dependant on task 1's finish date and an end date dependent on Task 3's finish date. I want Task 2's duration

    to expand automatically when task 3's finish date moves out. Project seems to keep the duration the same and pushes Task 2's start date out.

    I want the start date anchored and the duratiuon to expand automatically or else I have to manual change the duration on many tasks in my pp.

                                                      == Task 3 ====

    ====== Task 1 =====

                                         ====== Task 2 ======

                                         1FS, 3FF

                                         


    Steven R. Sparks


    Thursday, April 5, 2012 6:12 PM

Answers