Manage resource rate RRS feed

  • Question

  • Hi,

    how resource rates are manged.  resource has standard rate field what should i enter in that filed. Hourly Rate, Daily rate.

    What are available options. pls guide.

    thx


    iffi

    Thursday, July 6, 2017 10:26 AM

All replies

  • Hi Iffi (again),

    When you create a work resource in PWA (or in MS Project), you can enter an hourly rate and an overtime hourly rate. Labor costs are calculated using the work and this hourly rate.

    When editing the resource in MS Project Pro and double clicking on the resource to open the resource information, you can navigate to the cost tab. You'll see that the default rate entered in PWA is in the cost rate table A. You have up to 5 rate tables (A to E), meaning that you can have up to 5 rates per resource. Then in the task usage view for example, you can insert the cost rate table column and switch from A rate (default) to another one. For example a resource might be project manager on a project (rate A) and technical expert on another project (rate B). In this case, you'll use different rates.

    Another feature accessible from the resource information "cost" tab in MS project is the effective date. On the 5 rate tables, you can have effective dates, for example by year if you want to manage salary increase.

    • https://epmsource.com/2010/03/11/multiple-cost-rates-for-a-resource-in-the-same-project/
    • https://support.office.com/en-us/article/Enter-costs-for-resources-b4ced847-2655-4fa4-a621-3fc26fc81c88?ui=en-US&rs=en-US&ad=US
    • https://support.office.com/en-us/article/Standard-Rate-resource-field-1e99b07c-9b9d-41a2-be31-06f0297840f3


    Guillaume Rouyre, MBA, MVP, P-Seller

    Thursday, July 6, 2017 10:43 AM
    Moderator
  • Hi,

    Thanks for information, can we have rate table for overtime rate or overtime rate have just one rate.

    pls guide.

    thx


    iffi

    Thursday, July 6, 2017 11:20 AM
  • You can set overtime rate for each table and each effective dates within each table.


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller

    Thursday, July 6, 2017 11:41 AM
    Moderator
  • Hi,

    Cost Rate Table mentioned like A,B,C,Dand E.  For example any resource work as Project Manager, Technical Lead, Programmer so for that i have set three different rate but when any Project Manager add that resource in project cost rate table has option to select A,B,C.. how Project Manager know resource role Project Manager/Technical Lead/Programmer. 

    pls guide

    thx


    iffi

    Thursday, July 6, 2017 12:53 PM
  • I guess this is an organisational question, no tool related. When a PM starts a new project, he should know who is working for the project with which skills. You could always use the resource notes to map the rate tables with the skills.

    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller

    Thursday, July 6, 2017 1:24 PM
    Moderator