there are two possible reasons,
1. Due to the number of assignments (1,622)
2. Some bad assignment
Are you able to access the Ribbon?
Can you try to set the date range and the filters to reduce the load?
Another workaround:
Set a Rule to approve the updates automatically, later check the status.
Cheers. Happy troubleshooting !!! Sriram E - MSFT Enterprise Project Management