Gannt Progress RRS feed

  • Question

  • Hi!

    Is it possible to change the progress bar, so that instead of using % Complete, it uses Physical % Complete? 

    Thanks in advance!!

    Ignacio

    Wednesday, September 2, 2015 7:07 PM

Answers

  • Sure.  Just go into the Bar Styles dialog by right clicking on a blank area of the bar chart.  Then find the bar you want to modify (Task Progress, Critical Progress, etc.), and change the last column (the "To" column) from "Complete Through" to "Physical % Complete."  I would recommend that you add a new bar instead of editing a standard one, but you can do this.

    • Proposed as answer by John Hansleyton Saturday, September 5, 2015 3:26 PM
    • Marked as answer by isa7667 Monday, September 7, 2015 12:33 PM
    Wednesday, September 2, 2015 7:28 PM
  • As a complement of the good answer from Tom, you can display, on the right extremity of the bars, the “Physical % complete” value instead of the "% Complete" : Double click in a white area of the Gantt chart to open the Bar styles dialog, select the symbol of your bar, Click the Text tab and for “Right” select “Physical % Complete”.


    Gérard Ducouret [Project MVP], Certifié Project 70632, Certifié ITIL

    • Marked as answer by isa7667 Monday, September 7, 2015 12:33 PM
    Saturday, September 5, 2015 1:45 PM

All replies

  • Sure.  Just go into the Bar Styles dialog by right clicking on a blank area of the bar chart.  Then find the bar you want to modify (Task Progress, Critical Progress, etc.), and change the last column (the "To" column) from "Complete Through" to "Physical % Complete."  I would recommend that you add a new bar instead of editing a standard one, but you can do this.

    • Proposed as answer by John Hansleyton Saturday, September 5, 2015 3:26 PM
    • Marked as answer by isa7667 Monday, September 7, 2015 12:33 PM
    Wednesday, September 2, 2015 7:28 PM
  • As a complement of the good answer from Tom, you can display, on the right extremity of the bars, the “Physical % complete” value instead of the "% Complete" : Double click in a white area of the Gantt chart to open the Bar styles dialog, select the symbol of your bar, Click the Text tab and for “Right” select “Physical % Complete”.


    Gérard Ducouret [Project MVP], Certifié Project 70632, Certifié ITIL

    • Marked as answer by isa7667 Monday, September 7, 2015 12:33 PM
    Saturday, September 5, 2015 1:45 PM