Master Project Resource Utilization RRS feed

  • Question

  • I am trying to use the resource utilization view for resource leveling.  Is there a way to combine all hours for a resource over multiple projects in this view? right now I have two projects linked to the master and it shows an entry for each project for the same id, resulting in two entries verses combining all hours for the id. I am using 2007.
    Monday, February 18, 2013 9:31 PM

All replies

  • Hello M2AZ,

    Project will not automatically consolidate usage from multiple project files.  See:

    http://office.microsoft.com/en-us/project-help/share-resources-using-a-resource-pool-HA010214871.aspx

    for details on creating resource pools to view consolidated data.

    Julie

    Tuesday, February 19, 2013 12:25 AM
    Moderator