Workspaces access rights and permission level RRS feed

  • Question

  • Hi,

    i'd like to give my project manager "manage permissions" on the project workspaces they create, how can I do that? I made some research and i found someone saying that the default come from PWA web Site, but it don't seem to be the case for me... I changed those permission levels and the changes does not reflect on my Workspaces, even after a manual synchronization. Our Workspaces are not stored in the same site collection as PWA, they are stored under http://project-server/projects/Workspaces, can it be the cause of my problem? I don't want to completly disable the synchro, because nothing at all get synchronized when you create the workspace.

    Any Idea?

    Thanks,

    Pierre-Nicolas

    Monday, April 4, 2011 7:58 PM

Answers

All replies