Earned value for work RRS feed

  • Question

  • Is there any concept similar to Earned value which relates to the earned value in work??? e.g: If i have a baseline work for a particular task A as 10hrs but the resource completed the task to 100% in 5 hrs so my actual work done is 5hrs but my earned value work for that particular task would be 10 hr.

    If there is a concept like this , how can we incorporate that in our microsoft project and create indicators for the same.

    Thanks & Regards

    Atul Lal

    Tuesday, March 19, 2013 7:48 PM

All replies

  • Its built in project as it is.  Earned value has costs (value) associate to it and not so much hours.  Project needs to have a Status Date set when calculating.

    Michael Wharton, MVP, MBA, PMP, MCT, MCTS, MCSD, MCSE+I, MCDBA
    Website http://www.WhartonComputer.com
    Blog http://MyProjectExpert.com contains my field notes and SQL queries

    Wednesday, March 20, 2013 2:10 AM
    Moderator
  • In the organization i am working , the earned value they want to calculate is for the hours/days and not costs

    eg : if a work has baseline work of 50 hrs but it was completed in 25hrs , they want to indicaate that they have earned the work of 50hrs in those 25 hrs. Is it possible to show in Project server???

    Thanks & Regards

    Atul Lal

    Wednesday, March 20, 2013 12:10 PM