Planned value (BCWS) does not update cost resources. The Earn value (BCWP) column contains values greater than BCWS RRS feed

  • General discussion

  • Planned value (BCWS) does not update cost resources. The Earn value (BCWP) Screen shot of task 3 with cost deatils.indicating missing permit fee of 110 usdcolumn contains values greater than BCWS  in some tasks, while we know that Earned value is just X% of the BCWS in particular date.  bBseline and status dates have been saved  but still does not work. I have noted in all tasks with cost resources BCWS does not update its total cost to include cost resources.
    Sunday, June 2, 2019 4:51 PM

All replies

  • kagwa --

    I have bad news for you, my friend.  Microsoft Project does not include the cost of Expense Cost resources in EVA calculations.  Sorry, but hope this helps.


    Dale A. Howard [MVP]

    Sunday, June 2, 2019 6:44 PM