    I have created an enterprise, number, task custom field and defined it to SUM to summary tasks.

    This works fine in Project Professional. This also works fine in PWA for group summary tasks (when the PWA view uses grouping). This doesn't work for regular summary tasks in a PWA view: I can see the values in the bottom-level tasks, but the field cells for the summary tasks remain blank.

    Any idea?

     

    Thanks,

    Barak

    Tuesday, October 18, 2011 1:09 PM

Answers

  • I am able to reproduce this in an older (less patched) version, but not in a fully up-to-date version.

    I suggest you look into installing Service Packs or updates as appropriate.


    Reid McTaggart Partner DeltaBahn LLC