Status Update Hours Differ From Timesheet Hours RRS feed

  • Question

  • Project resource has entered 1 hour against a task and submitted their timesheet.  Our process then has the Status Updates go to the Project Managers for review and acceptance into their plans prior to the Resource Managers actually approving the entire timesheet. 

    My question is that when the PM reviews the status update via the approval center they see the time entered for this task as 0.09 hours vs. the 1 hour entered for this task on the timesheet.  What can cause this?

    Thank you!


    lbr

    Monday, November 25, 2013 5:16 PM

All replies

  • Is there any chance the Units measurement (ribbon) in the Approval view has been changed to days instead of hours?

    Wednesday, December 18, 2013 11:14 PM