  • Question

  • Is there a way where approvals can be initiated on change in baseline for certain types of projects. Below are the requirement details:

    1. Environment: Project Online

    2. Different types of projects (EPTs)

    3. Project managers have permission to save baselines

    4. Need an approval mechanism whenever project managers change baseline for certain types of projects

    If not possible exactly as mentioned above then are there any alternatives to manage this requirement.


    Abhijeet Mohite, PPM Consultant | abhijeetm@outlook.com

    Monday, July 24, 2017 8:26 AM

All replies

  • There's no built in mechanism to fulfill the requirement. However, you can try to solve it programmatically using VBA in the client to trigger an action.

    Best regards,

    Julian, PMP, MCP, MCSA, MCSE

    Project Blog: Https://project-brain.com
    Tuesday, July 25, 2017 6:19 AM