Reassign a Task to another resource RRS feed

  • Question

  • I am using Project Pro 2010 and Project Server 2010.  I was told that reassigning tasks to a new resource through Project Pro can cause an error message when team members access My Work in the PWA.  What is the best practice for changing the resource on a task?  Do you just switch the resource under the resource names column in Project Pro 2010, or do you reassign through the PWA?  If the best way is through the PWA can I as the admin. do it or do  I have the current resource do it  in My Work and send to the PM for approval?

    Long Live America


    Thursday, September 6, 2012 8:26 PM

Answers

  • Vassily --
     
    Whoever told you not to reassign tasks to a new resource in Project Professional is sadly mistaken.  Out of curiosity, what type of error message does this user claim team members will see?  Anyway, a best practice I recommend for replacing the current resource is to do the following:
      • Select the task in question.
      • Click the Resource tab to display the Resource ribbon and then click the Assign Resources button.
      • In the Assign Resources dialog, select the resource currently assigned to the task and then click the Replace button.
      • In the Replace Resource dialog, select the new resource and then click the OK button.
      • Click the Close button to close the Assign Resources dialog.
    Hope this helps.

    Dale A. Howard [MVP]
    VP of Educational Services
    msProjectExperts
    http://www.msprojectexperts.com
    http://www.projectserverexperts.com
    "We write the books on Project Server"

    Friday, September 7, 2012 1:08 AM
    Moderator

All replies

  • You can you the substitute resource under the resources tab in Project Pro.  
    Thursday, September 6, 2012 9:59 PM
  • Vassily --
     
    Whoever told you not to reassign tasks to a new resource in Project Professional is sadly mistaken.  Out of curiosity, what type of error message does this user claim team members will see?  Anyway, a best practice I recommend for replacing the current resource is to do the following:
      • Select the task in question.
      • Click the Resource tab to display the Resource ribbon and then click the Assign Resources button.
      • In the Assign Resources dialog, select the resource currently assigned to the task and then click the Replace button.
      • In the Replace Resource dialog, select the new resource and then click the OK button.
      • Click the Close button to close the Assign Resources dialog.
    Hope this helps.

    Dale A. Howard [MVP]
    VP of Educational Services
    msProjectExperts
    http://www.msprojectexperts.com
    http://www.projectserverexperts.com
    "We write the books on Project Server"

    Friday, September 7, 2012 1:08 AM
    Moderator
  • Thanks Dale.  The error we were seeing was the "unknown error has occured" when they clicked on "My Work".  The person said it was happening because of re-assigning tasks to a new resource.  The error fixed itself within a couple days (not sure why)

    Long Live America

    Monday, September 10, 2012 1:24 PM
  • Vassily --
     
    The person is in error.  Like you, I am clueless about what caused the error, and how the error managed to resolve itself.  :)
     

    Dale A. Howard [MVP]
    VP of Educational Services
    msProjectExperts
    http://www.msprojectexperts.com
    http://www.projectserverexperts.com
    "We write the books on Project Server"

    Tuesday, September 11, 2012 1:20 AM