PWA 2013 Unlinking subprojects RRS feed

All replies

  • Hi,

    If you just need to unlink the subproject, keeping it in the master plan:

    1) Open the master project in Project Pro
    2) Select the subproject and right mouse click on “Information” to open the Information window
    3) In the Information window, select the “Advanced” tab
    4) On the Advanced tab, deselect the checkbox “Link to project” and click “OK”
    5) When prompted to save changes to the subproject, click “Yes”


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller |

    Monday, August 3, 2015 3:23 PM
    Moderator
  • I have just used this method to unlink two subprojects from the master. However, now the master project is considered a project rather than a 'window' into the subprojects. How can I unlink it from my enterprise resource pool? I don't want people booking timesheets to this master project as it is now not needed.

    Kind regards

    Amy

    Friday, January 22, 2016 9:36 AM