Earned Value with Project Web App 2013? RRS feed

  • Question

  • Hi folks,

    Earned Value in Project Client is quite fine, the choice of calculate against actual or status date is a nice feature. But using Project Web App I lack the option of setting the status date - is EVA in Project Web App 2013 really restricted to the actual date? Or is the status date set automatically by approved task updates?

    Thanks

    Olaf


    Thursday, July 31, 2014 10:02 AM

Answers

  • Hi Olaf,

    Unfortunately the status date cannot be set from PWA, and there is no automatic update behind. The intent is that the PM updates the status date and the tasks in MS Project Pro and the team members and executives can consult EVA from PWA.


    Hope this helps,


    Guillaume Rouyre, MBA, MCP, MCTS |

    • Marked as answer by olaf.lischke Monday, August 4, 2014 5:19 PM