Filter on overdue Deadline (Project Pro 2010) RRS feed

  • Question

  • Hello,

    I'm trying to built a filter to list the tasks for which the Finish date is after their deadline.

    In a filter, the following criteria doesn't work (it displays nothing):

    Finish ... is greater than ... Deadline.

    While in a custom field the following formula works fine:

    [Finish] > [Deadline]

    Why ???

    Thanks for your help

    Sunday, December 2, 2012 10:11 AM

Answers

  • Hi,

    are you currently working with 2010? In 2010, I can only get this filter working with Scheduled Finish, with Finish I get an error. Here a screenshot, with highlight to display all tasks. Am I doing something different or are you using another version?

    Regards
    Barbara

    • Marked as answer by WLID1966 Sunday, December 2, 2012 10:32 AM
    Sunday, December 2, 2012 10:20 AM
    Moderator
  • Hi,

    with 2010, you are allowed to enter any text into Finish. Therefore it is changed to a tesxt field. Whenever you enter a valid date into Finish, Scheduled Finish and Finish will match - from point of value, but not technical format. When you enter a text, you will find a default value (like Project Start Date) in Scheduled Finish, because Project can't schedule a finish date.

    Regards
    Barbara

    Sunday, December 2, 2012 10:52 AM
    Moderator

All replies

  • Hi,

    are you currently working with 2010? In 2010, I can only get this filter working with Scheduled Finish, with Finish I get an error. Here a screenshot, with highlight to display all tasks. Am I doing something different or are you using another version?

    Regards
    Barbara

    • Marked as answer by WLID1966 Sunday, December 2, 2012 10:32 AM
    Sunday, December 2, 2012 10:20 AM
    Moderator
  • Hi Barbara,

    Thanks a lot: that works with Scheduled Finish!

    Another question could be: Why?

    Sunday, December 2, 2012 10:34 AM
  • Hi,

    with 2010, you are allowed to enter any text into Finish. Therefore it is changed to a tesxt field. Whenever you enter a valid date into Finish, Scheduled Finish and Finish will match - from point of value, but not technical format. When you enter a text, you will find a default value (like Project Start Date) in Scheduled Finish, because Project can't schedule a finish date.

    Regards
    Barbara

    Sunday, December 2, 2012 10:52 AM
    Moderator
  • By the way: the same affects for example Duration and Start, related fields are Scheduled Duration and Scheduled Start.

    Regards
    Barbara