Report showing at which stage each project is in the master schedule. RRS feed

  • Question

  • Hi All,

    I have a master schedule which has approx. 350 projects listed in a single file and each project is around 10 lines (high level). At Level 2 I have Plan, Deliver & Learn for each projects as a summary tasks. Now I have to generate the report which shows how many project are in each stage, for example Plan=150, Deliver=100 and Learn=100.

    Is there a chance I can get such report from the MS Project rather than transferring it into excel? I have inserted a text column and typed P, D & L against Plan, Deliver & learn respectively thinking that MSP might be able to count no. of P's, D's & L's.

    Wednesday, July 19, 2017 12:25 AM