Master Project Indenting Sub Projects

Question
-
Running Project Server 2010 with SP1. When adding multiple sub-projects in a master project, each sub-project get added as a "child" (e.g. indented to the right) of the proceeding sub-project. I can't shift left. What am I doing wrong?
Jim SipeWednesday, September 28, 2011 3:49 PM
Answers
-
Hi Jim,
You will need to collapse the sub project 1 & in next row, you can insert the sub project 2. if you keep sub project 1 as expanded, sub project 2 will be added as a sub project of sub project 1.
Thanks, Amit Khare |EPM Consultant| Blog: http://amitkhare82.blogspot.com http://www.linkedin.com/in/amitkhare82Wednesday, September 28, 2011 4:00 PM
All replies
-
Hi Jim,
You will need to collapse the sub project 1 & in next row, you can insert the sub project 2. if you keep sub project 1 as expanded, sub project 2 will be added as a sub project of sub project 1.
Thanks, Amit Khare |EPM Consultant| Blog: http://amitkhare82.blogspot.com http://www.linkedin.com/in/amitkhare82Wednesday, September 28, 2011 4:00 PM -
WOW, so simple
Thanks for the help
Jim SipeWednesday, September 28, 2011 4:26 PM -
:) Yes, It is.
You are welcome Jim -
Thanks, Amit Khare |EPM Consultant| Blog: http://amitkhare82.blogspot.com http://www.linkedin.com/in/amitkhare82Wednesday, September 28, 2011 4:39 PM