Master Project Indenting Sub Projects RRS feed

  • Question

  • Running Project Server 2010 with SP1. When adding multiple sub-projects in a master project, each sub-project get added as a "child" (e.g. indented to the right) of the proceeding sub-project. I can't shift left. What am I doing wrong?
    Jim Sipe
    Wednesday, September 28, 2011 3:49 PM

Answers

  • Hi Jim,

    You will need to collapse the sub project 1 & in next row, you can insert the sub project 2. if you keep sub project 1 as expanded, sub project 2 will be added as a sub project of sub project 1.  
    Thanks, Amit Khare |EPM Consultant| Blog: http://amitkhare82.blogspot.com http://www.linkedin.com/in/amitkhare82
    • Marked as answer by Jim Sipe Wednesday, September 28, 2011 4:21 PM
    • Unmarked as answer by Jim Sipe Wednesday, September 28, 2011 4:22 PM
    • Marked as answer by Jim Sipe Wednesday, September 28, 2011 4:22 PM
    Wednesday, September 28, 2011 4:00 PM

All replies

  • Hi Jim,

    You will need to collapse the sub project 1 & in next row, you can insert the sub project 2. if you keep sub project 1 as expanded, sub project 2 will be added as a sub project of sub project 1.  
    Thanks, Amit Khare |EPM Consultant| Blog: http://amitkhare82.blogspot.com http://www.linkedin.com/in/amitkhare82
    • Marked as answer by Jim Sipe Wednesday, September 28, 2011 4:21 PM
    • Unmarked as answer by Jim Sipe Wednesday, September 28, 2011 4:22 PM
    • Marked as answer by Jim Sipe Wednesday, September 28, 2011 4:22 PM
    Wednesday, September 28, 2011 4:00 PM
  • WOW, so simple

    Thanks for the help


    Jim Sipe
    Wednesday, September 28, 2011 4:26 PM
  • :) Yes, It is.
    You are welcome Jim - 
    Thanks, Amit Khare |EPM Consultant| Blog: http://amitkhare82.blogspot.com http://www.linkedin.com/in/amitkhare82