Default cost for each task RRS feed

  • Question

  • Hello All,

    We are on Project Server 2010 version.

    Is there a way to default cost of each task to $1 (other than the PMs updating it everytime they add a new task?) ? Our resource cost are all $0 and we would like to keep it that way.

    Thanks

    Raja

    Friday, August 17, 2012 2:01 PM

Answers

  • Not with the default field Cost. You could with a "Custom" cost field. 


    Prasanna Adavi, PMP, MCTS http://thinkepm.blogspot.com

    • Marked as answer by Raja Bharathi Friday, August 17, 2012 2:43 PM
    Friday, August 17, 2012 2:21 PM
    Moderator

All replies

  • Not with the default field Cost. You could with a "Custom" cost field. 


    Prasanna Adavi, PMP, MCTS http://thinkepm.blogspot.com

    • Marked as answer by Raja Bharathi Friday, August 17, 2012 2:43 PM
    Friday, August 17, 2012 2:21 PM
    Moderator
  • Thats what I thought, I wanted to confirm from the experts! Thanks!
    Friday, August 17, 2012 2:43 PM