Domain Migration RRS feed

  • Question

  • Dear Support,

    Our environment contains 2 domains (Domain A and B) with a trust relationship and we have Project Server 2010 which is joined to domain B and the developer machines joined to domain A ,we'll migrate domain A to be domain C and the domain administrator will move the AD users from the domain A to the Domain C with the same SID and there will be trust relationship between Domain B and C then the old A Domain will be deleted, 

    My question is will Project Server work with the same users (i.e. will Project Server use same SID) or what is your advice because we need less headache and we need to keep all the old history and security permissions of the old users

     

    Regards,

    Sameh Henry

    Wednesday, March 9, 2011 3:51 PM

Answers

  • Yes. You can keep your old history and security permissions of the old users.

    Provided....

    Existing user configuration is DomainA\Username...It should be modified to DomainC\Username.

    At the same time the PWA root site should have all the new users (Meaning new domain \ users)

     


    Cheers. Happy troubleshooting !!! Sriram E - MSFT Enterprise Project Management
    Friday, March 11, 2011 9:27 PM