    I've been having an issue where Project removes the option to filter by 'late' tasks in the drop down menu. When I go into 'more filters' I can see the late task option however it will not apply the filter.

    Is this a common issue? If so, is there a way to rectify the problem?

    Thanks,

    Ruairidh

    Wednesday, May 20, 2015 2:20 PM

All replies

  • Hi,

    Have you tried to click on more filter, edit the late tasks filter and check the "show in menu" option?


    Hope this helps,


    Guillaume Rouyre, MBA, MVP, P-Seller |

    Wednesday, May 20, 2015 2:28 PM
    Moderator
  • When you say it "will not apply the filter" do you mean that all tasks are still visible or no tasks are visible?  If you add the Status field to the view - does it show any tasks with a status of Late?
    Wednesday, May 20, 2015 4:49 PM