filling the task in project server 2010 RRS feed

  • Question

  • What is the correct way of creating the projects in project server 2010? I want to ask that first we have to fill the duration or start date? and what is the relation of this with auto and manual schedule?
    Saturday, November 3, 2012 11:24 AM

Answers

  • Whenever u start upon building a project, first and foremost populate the project information in the Project tab. Then u can build the WBS.

    Let me answer ur second part of the Q first. The auto schedule determines ur start and finish dates automatically whereas the manual schedule you will have to key in the information.

    The duration controls your dates. Default the dates will set according to your Start date entered in the project information when the task is Auto scheduled. U can set the start date also but it will just add up a constraint of "Start no earlier than".

    For more infor u can read this link: http://technet.microsoft.com/en-us/library/gg597651.aspx


    Cheers, Amit Wairkar