Date settings in resource center in PWA 2013 RRS feed

  • Question

  • Hi everybody!!

    I would like to know if it's possible to set for a resource on PWA a start date and an end date business activity, without affecting the project. 

    Let me explain: I put  a resource (resource 1) in a team on February 2014, while another (resource 2) has completed the activities in January 2014. 

    In the resource center, if I select the period October 2013 - March 2014, the capacity of these two resources is considered for the whole time, while I would like that, for the period of October-November-December-January, resource 1 has capacity 0 and resource 2 has capacity 0 for period February-March 2014.

    Is it possible to set the resource-level features that take this discrimination? If so, how?

    It's a difficult question and perhaps I have not explained well! 
    Thanks anyway for the help


    Friday, February 7, 2014 3:25 PM

Answers

  • Hi Salentina,

    You can open (check-out) resources from the resource center in Project Pro. Then double-clicking on resource, you'll open resource information dialog box.

    In the General tab, you can set time intervals with specific % of availability for each interval:

    Finally just validate your changes, save and check-in the resource(s).

    Hope this helps.


    Guillaume Rouyre - MBA, MCP, MCTS


    Friday, February 7, 2014 7:25 PM